集美大学船闸水运工程 - 图文(3)
《水运施工》课程设计 2013.3.7.
6、渗流量计算
位置截面12上游引航道直线段345678上游导航段上闸首89910101112闸室13141516下闸首下游导航段16171718181920下游引航道直线段212223242526开挖高度左侧10.6910.43110.48510.47610.3119.4849.0379.03710.89210.89212.71112.71111.97311.0297.0266.6527.8298.518.5111.74611.74612.798.4018.4016.8798.269.2499.5589.3778.947.8247.824右侧10.68410.4810.37710.3710.31310.1379.9889.9889.8049.80414.34314.3438.5877.6737.7227.6558.3098.2978.2977.4617.46112.6239.1949.1948.6589.0519.3469.0418.5467.9857.6177.617左侧9.999.7319.7859.7769.6118.7848.3378.33710.19210.19212.01112.01111.27310.3296.3265.9527.1297.817.8111.04611.04612.097.7017.7016.1797.568.5498.8588.6778.247.1247.124渗流高度右侧9.9849.789.6779.679.6139.4379.2889.2889.1049.10413.64313.6437.8876.9737.0226.9557.6097.5977.5976.7616.76111.9238.4948.4947.9588.3518.6468.3417.8467.2856.9176.9174.53744.99154.24795.09037.62574.58864.91864.91864.324.323.363.365.00724.98323.76443.8823.40013.17343.17343.40013.40014.30974.30975.92773.99774.62084.72834.19173.86796.82694.238937.8116666741.5958333335.3991666742.4191666763.547538.2383333340.9883333340.988333333636282841.7266666741.5266666731.3732.3528.3341666726.44526.44528.3341666728.3341666735.9141666735.9141666749.397533.3141666738.5066666739.402534.9308333332.232556.8908333335.32416667挖槽段图上长度挖槽段长度挖槽段宽度5959595959595959592646462626262626262646462659595959595959595959段渗流斜面面积左侧右侧 段渗流底面总面积 渗流系数左斜面右斜面 底面 0.0180.0180.0180.0180.0180.0180.0180.0180.00720.00720.00720.00720.0180.0180.0180.0180.0180.00720.00720.00720.00720.0180.0180.0180.0180.0180.0180.0180.0180.0180.018斜面 77.47179447渗流量底面 40.15599斜+底 117.62778452100.739827总计372.8419392373.654892230.8883330.1035717860.103988707405.8921417404.66506462454.1541670.1015588850.100971702346.2215496342.43383882088.5508330.1020043560.09986739411.1901921408.98439542502.7308330.1002704080.099219084584.4781313605.28993753749.30250.0897583040.096822047327.3392525358.00639582256.0616670.0744710710.093378905341.7197350366.9120336.3080380.699642418.3116670.0685537240.0917600780327.7440382.004009360128800000000.1098045920.0876483740.0641507950.09178931382.0816735444.174775126.256448569.5140798937.593915107.107994981.8092654845.049155126.8584205111.067176667.487445178.554621657.8075498958.359189069.0148512056.6383104091.1348454755.074326421.2543670628.555409735.4659330935.71255505014.5896931077.4166064040.6091143.5296106.739209.2736019.5280819.4344814.6811615.139813.260394.95050409.3842760098.41665989101.888799075.7540512065.91191040110.662925574.508806435.9355270643.695209748.7263230940.66305905023.973969100450.6897267310.02913331084.8933330.147172040.080011575345.8133167290.582851079.6933330.1032036030.066711254192.58043211.585175206.53545000342.81865219.229245235.5727200.902665000406.343835815.62841.1687.570000.034758560.0664169990.0507462120.0756380660.090481690.084741924000000211.6420579215.4246692736.68833330.0811495280.08490801312.979205191.56730081303.3716670.0439658880.004328945355.3886363366.62977042118.9358330.1042495680.1101042462914.45250.0229305480.06549540538.140845115.557451434.4746733252.46014586.9348183221.8535869635.37964557.2332319642.640187951.12294740.8940841.84545583.534267992.968402228.8516679271.66037211965.5358330.0201363130.063481317310.1519467327.24890672271.8933330.0606044320.072860764342.9396588334.66513382324.74750.0780976850.072729876306.2560813282.71269962060.9191670.0796824640.061734874272.6386013243.85497881901.71750.0718093280.045441227437.0353817403.98180753356.5591670.0492288990.029103676251.6493633244.33726082084.1258330.0299627740.02202521341.8564718537.09654578.9530168530.6590640734.23091564.8899790733.2721259960.41806593.6901909912.921693237.51426550.4359582《课程设计任务书》 11
《水运施工》课程设计 2013.3.7.
7、最大排水量计算 工程部位上直线段上导航段上闸首闸室下闸首下导航段下直线段合计渗流量(m3/h)856.710775.7540565.91191354.191923.97397115.5575608.63992100.74日最大降水量(mm/d)109.3109.3109.3109.3109.3109.3109.3-----------降水面积(m2)29956.133611.912623.49313395.382567.5563464.03529594.08最大排水总量(m3/h)993.135992.2032977.85974415.196735.66705131.3332743.416385212.582488.812(四)施工组织设计
1、有效工日计算
由于降雨、温度等的限制,每月可以施工的天数不同,不同的施工程序每月可以施工的天数也不一样。具体有效工日计算表如下: 表15 有效工日分析 有效工日计算 分部工程 土方开挖 月份 当月总天数 降水量停工 节假日天数 停工的总天数 有效工日 混凝土工程 降水量 节假日天数 停工的总天数 有效工日 降水量 浆砌块石 节假日天数 停工的总天数 有效工日 降水量 土方回填 节假日天数 停工的总天数 有效工日 调整工日 降水量 安装 节假日天数 停工的总天数 有效工日 X年 3月 4月 5月 6月 7月 8月 9月 31 1 4 4 27 0 4 4 27 0 4 4 27 3 4 4 27 27 0 4 4 27 30 2 4 4 26 0 4 4 26 0 4 4 26 6 4 6 24 24 0 4 4 26 31 7 6 7 24 1 6 6 25 1 6 6 25 16 6 16 15 18 1 6 6 25 30 9 4 9 21 2 4 4 26 2 4 4 26 18 4 18 12 18 2 4 4 26 31 6 5 6 25 1 5 5 26 1 5 5 26 16 5 16 15 18 1 5 5 26 31 14 4 14 17 3 4 4 27 3 4 4 27 26 4 26 5 18 3 4 4 27 30 11 4 11 19 2 4 4 26 2 4 4 26 19 4 19 11 18 2 4 4 26 10 31 6 6 6 25 1 6 6 25 1 6 6 25 11 6 11 20 20 1 6 6 25 11 30 4 4 4 26 0 4 4 26 0 4 4 26 10 4 10 20 20 0 4 4 26 12 31 2 4 4 27 0 4 4 27 0 4 4 27 5 4 5 26 26 0 4 4 27 X+1年 元月 31 2 5 5 26 0 5 5 26 0 5 5 26 5 5 5 26 26 0 5 5 26 注:降雨天数与假日数取大值,气温不符合均采取措施而不停工。 《课程设计任务书》
12
《水运施工》课程设计 2013.3.7.
2、推土施工组织分析
开工初期,先用推土机将场地进行初步整平,布置4辆T1-100推土机对各个施工段进行初步整平工作。推土工作包括在施工前准备工作中。推土厚度为20cm。推土施工组织如下:先集中4台推土机对上下闸首段进行推土,再集中对闸室段推土,然后4台推土机分为两队,每队为2台,先后对上下导航段,上下引航道直线段进行推土。在施工前一次推完约5天左右。再有10天左右时间进行施工队、机械的调迁,材料购买等工作,接下来正式开始施工。推土机械布置及人员配备见下表:
开挖面积m2工程量m3施工前准备初 …… 此处隐藏:5687字,全部文档内容请下载后查看。喜欢就下载吧 ……
相关推荐:
- [实用模板]第八章:法国“新浪潮”与“左岸派”
- [实用模板]2021年北京上半年临床医学检验技师生物
- [实用模板]SAP GUI 7.10客户端安装配置文档
- [实用模板]2001年临床执业医师资格考试综合笔试试
- [实用模板]36机场工作实用英语词汇总结
- [实用模板](一)社会保险稽核通知书
- [实用模板]安全教育主题班会材料
- [实用模板]濉溪县春季呼吸道传染病防控应急演练方
- [实用模板]长沙房地产市场周报(1.30-2.3)
- [实用模板]六年级数学上册典中点 - 图文
- [实用模板]C程序设计(红皮书)习题官方参考答案
- [实用模板]中国证监会第一届创业板发行审核委员会
- [实用模板]桥梁工程复习题
- [实用模板]2011学而思数学及答案
- [实用模板]初中病句修改专项练习
- [实用模板]监理学习知识1 - 图文
- [实用模板]小机灵杯四年级试题
- [实用模板]国贸专业毕业论文模板
- [实用模板]教育学概论考试练习题-判断题4
- [实用模板]2015届高考英语一轮复习精品资料(译林
- 00Nkmhe_市场营销学工商管理_电子商务_
- 事业单位考试法律常识
- 诚信教育实施方案
- 吉大小天鹅食品安全检测箱方案(高中低
- 房地产销售培训资料
- 高一地理必修1复习提纲
- 新概念英语第二册lesson_1_练习题
- 证券公司内部培训资料
- 小学英语时间介词专项练习
- 新世纪英语专业综合教程(第二版)第1册U
- 【新课标】浙教版最新2018年八年级数学
- 工程建设管理纲要
- 外研版 必修一Module 4 A Social Surve
- Adobe认证考试 AE复习资料
- 基于H.264AVC与AVS标准的帧内预测技术
- 《食品检验机构资质认定管理办法》(质
- ABB变频器培训课件
- (完整版)小学说明文阅读练习题及答案
- 深思洛克(SenseLock) 深思IV,深思4,深
- 弟子规全文带拼音